The conversion process, step by step
Based on the Department of Health steps summarized by Wastewater Alternatives & Innovations (waicleanwater.org):
- Hire a Hawai‘i-licensed civil engineer to evaluate the site (including a percolation test) and design the system.
- Engineer submits plans to DOH Wastewater Branch for review. One Maui installer reports this usually takes about 4–6 weeks.
- Hire a licensed contractor holding an A, C-9, C-37, C-37a, or C-43 license. Verify the license with DCCA’s license search.
- Construction — one Maui installer reports about two working weeks on average, longer with rock or larger systems. The old cesspool is pumped, demolished and backfilled.
- Final inspection and approval — the engineer submits the final report and contractor certification; DOH issues an Approval to Use.
Some contractors handle engineering and permitting as a turnkey package; others ask you to bring approved plans. Our form asks which situation you’re in.